Full Story
Paladin ready to mine uranium in Nam
WINDHOEK - Paladin Resources Ltd has obtained bank approval for the debt component of the funding required to develop the Langer Heinrich Uranium Project in Namibia.
Paladin announced on Monday that it has accepted credit
committee-approved offers of financing totalling US$71 million
(about N$461,5 million), consisting of a seven-year project finance
facility of US$65 million and a standby cost overrun facility of
US$6 million.
The company said these facilities are being provided by Societe
Generale Australia branch (as lead arranger), Nedbank Limited and
Standard Bank of South Africa Ltd.
Drawdown on the financing is subject to completion of legal due
diligence and documentation, and fulfilment of other conditions
usually attached to this type of funding.
"This project-financing approval has been concluded only three
weeks after the mining licence was granted by the Namibian
Government.
This has been achieved as a result of the large amount of
preceding work that had been carried out to secure debt funding and
the focus and dedication by all involved," the Australian mining
company said.
According to the company, the Langer Heinrich Project is already
in its construction phase and site works are scheduled to start in
September.
The early-stage project development is currently being serviced
by funds raised via private placement in April this year.
With debt funding now in place, the company plans to raise
further equity for the balance of funds required to enable project
completion and provide sufficient working capital for the mining
start-up and the production ramp-up period.
-Nampa
The company said these facilities are being provided by Societe
Generale Australia branch (as lead arranger), Nedbank Limited and
Standard Bank of South Africa Ltd.Drawdown on the financing is
subject to completion of legal due diligence and documentation, and
fulfilment of other conditions usually attached to this type of
funding."This project-financing approval has been concluded only
three weeks after the mining licence was granted by the Namibian
Government.This has been achieved as a result of the large amount
of preceding work that had been carried out to secure debt funding
and the focus and dedication by all involved," the Australian
mining company said.According to the company, the Langer Heinrich
Project is already in its construction phase and site works are
scheduled to start in September.The early-stage project development
is currently being serviced by funds raised via private placement
in April this year.With debt funding now in place, the company
plans to raise further equity for the balance of funds required to
enable project completion and provide sufficient working capital
for the mining start-up and the production ramp-up period.-Nampa
